Installation method

Technical installation conditions for loading ramps


  PIT TYPE 1 AND 2


 

Type 1

In the upper edge of the wall of the pit made of reinforced concrete, the inverted L profile is firmly installed, on which the ramp is laid and connected by welding. The ramp is installed after concreting is completed.

Type 2

On the upper edge of the wall of the pit, a groove 100 and 150 mm wide is made of reinforced concrete, along which steel bars with a diameter of 20 mm are installed. A ramp rests on them and is joined by welding. The ramp is installed before the concreting is completed.

  PIT TYPE 3 AND 4


 

Type 3

Traditional installation system in a pit made of reinforced concrete with a rim reinforced with corner, upper and lower profiles. The pit can be the same depth as the ramp or with space below, to accommodate the electro-hydraulic drive of the ramp.

Type 4

The ramp bearing is built into the concrete, and the ramp is connected to the bearing by welding, at the end of concreting.

Dimensions of type 1 and 2 pits (in mm)
ramp width 2000 2000 2200 2200
ramp length 2500 3000 2500 3000
pit length „A“ -0 +10 mm 2500 2000 2500 3000
pit width „B“ -5 +5 mm 2070 2070 2270 2270
minimum pit height „C“ 550 550 550 550
Dimensions of pit types 3 and 4(in mm)
ramp width 2000 2000 2000 2200 2200 2200
ramp length (without tab) 2000 2500 3000 2000 2500 3000
pit length „A“ 2000 2500 3000 2000 2500 3000
pit width „B“ 2040 2040 2040 2240 2240 2240
pit height „C“ 550 550 550 550 550 550